LINCOLN — Lincoln Electric System has announced that the utility will begin the second phase of its South 56th Street Reliability Project in November, with moving lane closures on 56th Street that temporarily close individual lanes but allow traffic to pass through the work zone.
The South 56th Street Reliability Project demonstrates LES’ commitment to continuously improving service and reliability across the service territory. This project takes place along South 56th Street, from Everett Street to Elkcrest Drive. During the project's first phase, which began in 2023, LES installed underground distribution cables, placed new at-grade equipment and removed overhead distribution lines. This first phase of work is now substantially complete. Some poles temporarily remain, pending cable removals by some local communication companies.
In October, LES began preparations for the second phase of construction by clearing the transmission corridor to ensure a safe distance between trees and power lines. In November, the utility will contract with High Voltage, Inc. to replace the 115-kilovolt transmission line and many of its associated structures within the project area.
“The second phase of this project will renew aging infrastructure and increase the electrical capacity to support Lincoln’s growth,” said Tim Rajewski, project manager, Energy Delivery. “We’ll install taller transmission structures and position them further from the road, improving safety and reliability.”
Construction will begin in November by removing transmission lines and structures and then installing new steel poles and cables. This work is anticipated to require a moving lane closure, impacting southbound 56th Street traffic. High Voltage, Inc. will minimize traffic disruptions as much as possible while maintaining a safe work environment for crews.
“LES is dedicated to providing reliable electricity to our customers,” added Rajewski. “The South 56th Street Reliability Project is building our system reliability and resiliency as part of that dedication.”
The South 56th Street Reliability Project is expected to be completed in spring 2025.